PROJECT
MARTINREA Automotive Parts (Shanghai) Co.,LtdThe French-made CNC precision pipe bending machine needs to be relocated from the existing site to the new site. Since the equipment is fully imported, the manufacturer is worried that the equipment cannot be restored to its existing accuracy after relocation. After consulting with foreign equipment manufacturers, the manufacturer's quotation was expensive and exceeded the manufacturer's budget. The manufacturer found us, and we conducted an on-site investigation and a technical evaluation before relocation. It will take about 10 working days to complete the relocation and installation work. After the contract was signed, the electrical system backup and connection mechanism disassembly, equipment transportation, unloading and installation of the equipment were completed within 3 working days. The equipment was debugged in the following 2 working days, and the product trial production pass rate was 100%. It was highly praised by the foreign manager of the factory.